Four kilometres of anti-tank ditches dug along the border
According to Latvian public broadcaster LSM, construction of the Baltic Defence Line continues with ditches and concrete obstacles. However, the reported construction progress is not enough to assess defensive readiness.

Latvia is continuing to build anti-tank obstacles along its eastern border as part of the Baltic Defence Line, Latvian Television reported on 8 November. LSM carried the report. At the time of publication, Flank had found no independent confirmation of the stated quantities and deadlines.
The first 27 kilometres are scheduled for spring 2027
According to LSM, four kilometres of anti-tank ditches have been dug out of a planned total of 89 kilometres. The broadcaster gives spring 2027 as the deadline for completing the first 27 kilometres. This is a target in the construction schedule, not a result already achieved.
According to LSM, concrete obstacles known as “dragon’s teeth” are being installed alongside the ditches. The report says they are intended to impede the movement of a potential adversary’s vehicles.
What the reported length of the ditches tells us
In Flank’s assessment, the reported length reflects construction progress, but does not in itself show whether the sections can fulfil their defensive role. Anti-tank obstacles can slow or channel vehicle movements. Their effectiveness also depends on the terrain, surveillance, covering fire and the availability of forces able to respond.
LSM’s report does not specify whether the reported four kilometres constitute fully equipped positions, nor does it describe how they are integrated with other defensive measures. At the time of publication, Flank had found no official confirmation from the responsible Latvian institutions of the progress and deadlines. Further information may provide a fuller picture.
Sources
1 secondary report
Secondary reporting
Public Broadcasting of Latvia (LSM) · eng.lsm.lv
Latvia continues to secure eastern borderVerified media
Linked to this story
Related topics

Narva, EstoniaMilitary Infrastructure
First bunkers near Narva completed
Estonia is expanding the Baltic Defence Line in the north-east of the country. According to ERR, the concrete shelters are part of preparations for defence directly along the border with Russia.

LatviaMilitary Infrastructure
Dombrovskis announces two European drone centres in Latvia and the Netherlands
The two pilot centres are planned for 2027 and will cover drone and counter-drone technologies. The announcement concerns development and testing, not military capabilities already acquired.